Terms and stages of construction works

IMPORTANT NOTE. According to Croatian Legislation, any external construction works are prohibited on the Brach Island during the official tourist season, since June 01 till September 31, in order to create the most favorable tourist atmosphere.

First stage: : Apr – May 2015  

  • Parcel’s clean-up works and construction site equipments;

Second Stage: Oct 2015– May 2016 

  • Simultaneous beginning of the construction of all four villas in October 2015;
  • Before 31 May, 2016: completion of main external construction works, including excavation works, reinforced concrete constructions, block works and preparation of service lines and communications;

Third Stage: Oct 2016 – Dec 2016 

  • External and internal finishing works, connection of service lines and communications; landscape design, fence and gate mounting;
  • Final preparation of each villa and land plot for sale;